ASHLAND HEALTH CENTER
The previous hospital in Ashland, Kan. was in bad shape. “We were battling the overall building,” said Michael Mages, CEO of Ashland Health Center. When it was time to rebuild, the hospital sought a partner it could trust to “collaborate with our team, to develop a relationship with, someone to help make the best decisions we could make along the way,” said Mages. Hutton was that partner.
SERVICES
- Construction management at-risk
- Building information modeling
- Site coordination
- Pre-bond services
- Cost estimating
- Self-perform
DETAILS
The job was to replace an existing hospital with the design team at ACI Boland. Hutton successfully completed the 42,300-square-foot facility within 16 months.
DID YOU KNOW?
The largest wildfire in Kansas history, the Starbuck fire, came within a quarter of a mile of the hospital as it was being built.


MEDICAL ADVICE
Hutton kept the hospital staff involved in the process at every step. “They were always approachable anytime I had a question, and they were always on-site when I needed them,” said Mages. “I always felt as though I was educated in an appropriate way each time I had a question.”



“They were always approachable anytime I had a question, and they were always on-site when I needed them.”
MICHAEL MAGES
CEO, Ashland Health Center


URGENT CARE
Hutton completed the 42,300-square-foot facility within 16 months. “Hutton was focused on a drive for efficiency, focused on what we wanted, and focused on keeping the project moving forward,” said Mages. “I’m very pleased that Hutton was on our team.”